Proposed 275kV Transmission Line Double Circuit Loop In/Out into PMU Subang Jaya Town Centre (From KULW-KULS) & 132kV Transmission Line Double Circuit Loop In/Out PMU Subang Jaya Town Centre (From SJSS-NSDA)
WWEC is the main contractor for this project. The scope of work involves the design, supply, and erection of 275kV & 132kV Double Circuit LILO into the PMU Subang Jaya Town.
For this plant, the 275kV transmission line double circuit runs from KULW to KULS, covering a route length of approximately 1.5km. Additionally, the 132kV transmission line double circuit extends from SJSS to NDSA, with a route length of approximately 1.5km.
Another 132kV transmission line double circuit stretches from SJSS to SJTC/KTMB substation, with a route length of approximately 750m. The 2 x 24 cores optical ground wire (OPGW) also has a route length of approximately 1.5km.
Featured Projects
500kV Transmission Line – Pulau Indah to Olak Lempit
1,000 – 1200 MW Pulau Indah Combine Cycle Power Plant To 500/275/132kV Olak Lempit Substation
275kV Clearance Upgrade – DUKE Highway Section 1
Increasing Height Clearance of 275kV Transmission Line Crossing Expressway
132kV & 33kV Switchgear & Transformer Works – PMU Senai
Complete with Associated Civil Works for PMU 132/33kV Senai Extension (2x90 MVA)